Costs dialog in economic evaluation defines all the initial charges and running costs of the system in order to calculate total investment, yearly cost and energy cost.
Costs can be defined globally, by pieces, by installed Wc or by m².
You can work with any currency, and pass from one to another by a selection in the list box. The button "Rates" allows to adjust their relative parity. Choosing one of them as a reference, you can manually modify or download from internet the exchange rates or add new currencies.
Installation costs
This section determines direct and indirect installation costs of the system.
This includes component costs (modules, inverters, batteries, pumps, controllers, generator), expenses for studies and analysis, administrative fees (grid-connection cost, bank charges, permitting, taxes), insurances, land costs, substitution credit and subsidies. The number and type of PV involved components (PV modules, inverters, batteries, etc.) are automatically updated from the simulation parameters.
Depreciable asset :
An installation cost can be defined as depreciable, meaning that during each accounting period, a portion of this cost will be deductible from income. Depreciation rules definition is performed in Financial Parameters dialog.
Component and accessories costs are set as depreciable by default in Pvsyst. To set another cost depreciable :
- click on a cost to select it
- click on edit button
- check the depreciable checkbox from the opening dialog
Add/delete/update costs
The predefined cost list is fully customizable to take into account any specific cost of your system which is not present in the predefined list. You can add, remove, reorder or rename costs. You can also save defined cost list as template in order to reuse them in another project.
Select all
Selects all the investment costs to be deleted, edited or moved.
Unselect
all
Unselects all the selected costs. This button is disabled if no cost is selected.
Move up
Moves up selected costs. The investment costs list displayed in the printed report uses this order. This button is disabled if no cost is selected.
Move down
Moves down selected costs. The investment costs list displayed in the printed report uses this order. This button is disabled if no cost is selected.
Update cost
Opens the installation cost edition dialog to update properties (name, section, type) of a selected cost. This button is disabled if no cost is selected or more than one cost are selected.
![]() |
Opens the installation cost edition dialog to add a custom cost if it is not existing in the predefined list. |
![]() |
Deletes selected installation costs from the list. This button is disabled if no cost is selected. |
![]() |
Restores installation costs to Pvsyst default predefined cost list. |
![]() |
Loads cost list from a previously saved template file. |
![]() |
Saves all defined installation costs in a template file in order to be reused later or in a different project. |
![]() |
Prices can be defined for each component. When clicking this button, you may define your own prices for the components used, either for one piece, or discount price for several pieces. These prices may be either saved in your component library, or just kept for the current session, without modifying the component database. Prices can also be defined globally in price list dialog from component database. |
Operating costs
This section defines the annual running expenditures of the system.
The predefined cost list depend on the system type.
-For a grid-connected system, usually very reliable, they are limited to an annual inspection, eventually some cleaning of the collectors and the insurance fees. Some Inverter suppliers provide a long-term payable warranty, including replacement, which are assimilable to an insurance.
-For a stand-alone system, one should add a provision for the maintenance and periodical replacement of the batteries. This last contribution is calculated by the program as a function of the expected lifetime of the battery pack, calculated by the simulation. Moreover, when using an auxiliary generator the program computes the used fuel cost.
-For pumping systems, there is also a provision for pump replacement, their lifetime being usually of the order of a few years. And of course for the batteries when used in the system.
As for installation costs, operating costs are fully customizable to fit the specific needs of your system. The total sum of operating costs is called OPEX (for Operational Expenditure).
Select all
Selects all the operating costs to be deleted, edited or moved.
Unselect
all
Unselects all the selected costs. This button is disabled if no cost is selected.
Move up
Moves up selected costs. The operating costs list displayed in the printed report uses this order. This button is disabled if no cost is selected.
Move down
Moves down selected costs. The operating costs list displayed in the printed report uses this order. This button is disabled if no cost is selected.
Update cost
Opens the operating cost edition dialog to update properties (name, section, type) of a selected cost. This button is disabled if no cost is selected or more than one cost are selected.
![]() |
Opens the operating cost edition dialog to add a custom cost if it is not existing in the predefined list. |
![]() |
Deletes selected operating costs from the list. This button is disabled if no cost is selected. |
![]() |
Restores operating costs to Pvsyst default predefined cost list. |
![]() |
Loads cost list from a previously saved template file. |
![]() |
Saves all defined operating costs in a template file in order to be reused later or in a different project. |
Financial summary
The Total yearly cost is the sum of running costs and loan annuities (defined in Financial Parameters). It is an annual average value on project duration including the inflation rate if defined.
The LCOE (Levelized Energy Cost) is the price of the produced kWh. It takes into account the present value of future cashflows by applying a Discount Rate.
The formula used in Pvsyst for LCOE calculation is :
It = Investment and expenditures for the year (t)
Mt = Operational and maintenance expenditures for the year (t)
Et = Electricity production for the year (t)
r = Discount rate that could be earned in alternative investments
n = Lifetime of the system
The Payback period is the duration required to recover the initial investment.